Planned
Works are expected to start in early 2026 and take 4 months to complete, weather permitting.
Why we’re doing this
This pocket park was identified for upgrading as part of our ongoing park renewal program.
We developed a concept design for the park based on your feedback in early 2025.
What we’re doing
Works will include:
- building new and upgrading existing pathways with lighting on main paths
- installing seats
- adding garden beds with more plants
- building new and restoring existing retaining walls.
We’ll plant 4 new trees and remove 2 damaged trees. All other mature trees will be retained and protected during works.